Mataikona Road
Te Ara Mataikona
Masterton District Council has not gained funding for the business case (PDF, 19.3MB) developed for the Mataikona Road following community workshops and consultation in 2023. The project was led by the Council in partnership with Waka Kotahi, and working with hapū and iwi, and the community.
The Council is exploring our next steps and options, and will carry out workshops later in the year to continue the conversation with the community about these options.
Separately, resilience funding has been gained for work being carried out over the next two years. This work includes:
- Construction of Short Creek Tie-Back Retaining Wall and Rock Protection:
Construct a tie-back retaining wall and install rock protection at the location where the road was eroded away during Cyclone Gabrielle. - Te rerenga o Te Aohuruhuru/Suicide Rock realignment & Sandy Bay stabilisation:
Realign Te rerenga o Te Aohuruhuru/Suicide Rock section of the road by cutting back into the hill at the start, with temporary toe protection if required. The excavated material from the realignment would be used to backfill the road at Sandy Bay, raising it to the level of the revetment to help prevent sand buildup. Vehicle access would be formally limited to a to a single area, with dune buildup promoted in front of the rock groyne through planting. This could include installing a short groyne section to help direct the river mouth away from the revetment. Additionally, any spare material from Suicide Hill would be used to backfill and retreat the road at a point approximately 5.95km from the Masterton-Castlepoint Road turn-off. - Mataikona River erosion protection:
Installation of rock groynes to protect critical sections of the road from erosion and prevent further dropouts. - Road Reinforcement:
Strengthening of vulnerable sections of the road using rock riprap (rubble) – specifically, 100m, near Suicide Rock (6.2-6.7km from the Masterton–Castlepoint Road turn-off) and 80m at Middle Settlement.
This webpage will be updated to show progress and opportunities for community involvement. As part of the project, we will be meeting with key stakeholders, including hapū and iwi, as well as the wider Mataikona community, to discuss options and approaches.
Project background
Business Case
A business case (PDF, 19.3MB) was approved for work to improve the resilience of the Mataikona Road - an essential step in seeking funding for the work.
Masterton District Councillors agreed on 28 June 2023 to seek funding support for Option B in the business case, focussing on critical and high risk interventions, using a mix of coastal protection, retreat of the road (where practical and feasible), slope stabilisation, and retaining walls.
The business case and agreed option will be included in the 2024-34 Roading Asset Management Plan, and 2024-34 Long-Term Plan (LTP) which will be open for consultation with the community early next year.
A draft funding submission for the 2024-2027 National Land Transport Plan must be submitted to Waka Kotahi by next month (August 2023). The Council will not be advised of whether the funding submission is approved by Waka Kotahi until September 2024.
The preferred option has an estimated total cost of $32.8 million.
Where retreat options are proposed, these would be subject to land acquisition processes requiring consultation with landowners.
Further investigation of hybrid approach approved
On 9 November 2022, Masterton District Council (MDC) approved further investigation of a preferred hybrid option for Mataikona Road, as discussed at the community meeting on 3 September 2022.
After two public meetings, and consideration of likely costs, it was decided to take a look at a combined solution involving:
Strengthening options – priority strengthening (when and where this can be afforded).
Increased maintenance – where this is considered necessary in some sections.
Retreat options – where the road can be realigned inland (where possible and feasible)
Sandy Bay Drive has been identified as one potential area where the road could be retreated away from coastal erosion. No timelines or plans have been finalised. We are contacting landowners in the area as the first step in discussing feasibility and risks.
Among things to consider are that:
- raising the existing road would incur high costs and it would still be susceptible to coastal/river erosion requiring very expensive coastal protection
- taking advantage of the existing private road would be more economic for both landowners (through reduced responsibility for future maintenance) and the community, by utilising part of an existing as-built road.
Options considered
As set out at the 3 September meeting, the range of options considered were:

It was decided that:
- Options 8, 9 and 10 are not equitable to all communities along the road, are expensive and are not considered acceptable to the whole community.
- Options 5, 6 and 7 are considered unaffordable.
- Options 1 and 2 (“Do nothing” and “Do minimum”) are considered insufficient to meet the needs of the community.
The business case will focus on a combination of options 3, 4, and 5 in specific parts of the road.
Related Documents
- Community Meeting Presentation - 3 September 2022 (PDF, 2.9MB)
- Engagement Summary Report - August 2022 (PDF, 1.1MB)
- Intervention Options - August 2022 (PDF, 1.2MB)
- Mataikona Single Stage Business Case June 2023 (PDF, 19.3MB)
- Meeting Summary - 23 July (PDF, 335.3KB)
- Workshop Presentation - 23 July (PDF, 4MB)
Have Your Say
If you have questions or feedback about the project you can contact: communications@mstn.govt.nz.